Premium Emergency Support Centre 365 days 01695 213333

Emergency Support 365 days 01695 213333

Education

Reducing Fuel Consumption and Carbon Emissions for Tower Crane Operations

50% Fuel Reduction

The Challenge

Project Background

Our client required a reliable and resilient temporary power solution to operate multiple tower cranes on a construction site. Traditionally, large-capacity diesel generators were used to accommodate high motor-starting loads associated with tower crane operations. While effective, this approach resulted in high fuel consumption, elevated carbon emissions, and extended generator runtimes.

The challenge was to maintain operational performance while reducing fuel usage, emissions, and unnecessary generator operation, particularly outside standard working hours.

Original Power Solution

The original setup consisted of:

  • 2 × large-capacity diesel generators
  • Each generator supplied power via an integrated fuel tank and intermediary distribution board
  • Designed to handle high crane start-up loads
  • Operated for approximately 50 hours per week

Performance Characteristics

  • High fuel consumption due to oversized generators running at low efficiency during normal crane operation
  • Continuous running required to support both crane operation and aviation lighting
  • Elevated carbon emissions resulting from sustained fuel usage

This configuration, while reliable, was inefficient from both a fuel and environmental perspective.

Our Solution

Optimised Hybrid Power Solution

To address these challenges, the original generators were replaced with:

  • 2 × smaller-capacity generators
  • Integrated with Punch Flybrid hybrid energy storage units

The Punch Flybrid system is specifically engineered for high motor-starting applications, including:

  • Tower cranes
  • Construction hoists
  • Recycling equipment
  • Medical imaging systems (e.g. MRI scanners)

The Flybrid units manage short-duration peak loads during crane start-up, allowing the generators to be sized for true running load rather than peak demand.

Key Technical Improvements

  • Generator size reduced by 50%
  • Fuel consumption reduced by approximately 50%
  • Improved generator loading and operating efficiency
  • Lower emissions without compromising crane performance

Fuel and Carbon Reduction Outcomes

Fuel Consumption

  • Weekly fuel usage per machine reduced by half
  • Significant cumulative fuel savings achieved over the 21month hire period

Carbon Emissions

  • Carbon emissions reduced from approximately 26 tonnes per month with the original configuration to approximately 12.4 tonnes per month with the hybrid solution
  • Achieved a carbon reduction of more than 50% during crane operations

This reduction aligned with broader sustainability goals and supported compliance with evolving environmental expectations within the construction sector.

Out of Hours Energy Optimisation

To further enhance efficiency, an additional solution was introduced to eliminate unnecessary generator runtime outside working hours.

Battery Power Integration

  • A 5/15kW Husspod battery unit was deployed
  • Supplied power to:
    • Crane aviation lighting
    • Crane cab heater

Operating Schedule

  • Powered cranes during non-working hours (6:00pm – 7:30am)
  • Allowed generators to be completely shut down overnight

Benefits Achieved

  • Further fuel and carbon savings
  • Reduced engine wear and maintenance requirements
  • Improved site noise reduction
  • Enhanced environmental performance

The Results

  • Generator capacity reduced without affecting performance
  • Fuel consumption reduced by approximately 50%
  • Carbon emissions reduced by over 50%
  • Extended generator lifespan through reduced runtime
  • Improved sustainability credentials across a long-term project
  • Reliable power supply maintained throughout a 21month hire period

In Summary

By adopting a hybrid generator and battery-supported power strategy, our client successfully transitioned from a traditional high-consumption model to a more efficient, lower-carbon solution. The use of Punch Flybrid technology allowed for smaller generators, improved efficiency, and substantial environmental benefits over the project lifecycle.

Ready to Power Your Next Project?

Every site has different power requirements. Whether you need temporary power for construction, infrastructure or emergency backup, Stuart Energy supports sites with reliable, bespoke solutions. Our team can help identify the right power and energy solution for your site.

Get in Touch to Discuss Your Requirements Today